Renewable Energy

(asked on 4th June 2025) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to (a) manage and (b) accelerate the connection of the renewable energy projects in the transmission queue.


Answered by
Michael Shanks Portrait
Michael Shanks
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 13th June 2025

We are working closely with Ofgem and the network companies to develop and deliver fundamental reform of the grid connections process. National Energy System Operator (NESO’s) proposals for connections reform were approved by Ofgem on 15 April.

These reforms will release up to 500GW of capacity from the oversubscribed connections queue, enabling accelerated connections for renewable energy projects that are ready and aligned with our strategic needs, as set out in the Clean Power 2030 Action Plan.