A483

(asked on 1st June 2015) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, when he last discussed the progress of the A483 upgrade with Highways England; and what the outcome of that discussion was.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 9th June 2015

There have been no discussions on the A483 upgrade. Progress on the A55/A483 pinch point scheme was discussed with Highways England in February 2015. The outcome of the discussion was that the completion date for the scheme would be rescheduled to 10 May 2015, as set out in the answer of 2 March (UIN 225319). The scheme completion date has since been rescheduled to 28 June 2015.