Question to the Department for Transport:
To ask the Secretary of State for Transport, with regard to the November 2015 Report from Sir Peter Hendy on the replanning of Network Rail's Investment Programme; how many of the (a) 79 projects to be delivered in CP5 and (b) eight sub-projects of the Great Western Electrification programme (i) were completed in CP5, (ii) have been completed so far in CP6, (iii) are planned to be completed by the end of CP6 (a) are not expected to be completed by the end of CP6.
The Department is just over one year into the CP6 period and continues to progress its plans. To date five projects have been completed in CP6.
Network Rail publish on a quarterly basis all schemes in delivery. The latest published report can be found at:
The DfT also published an update in October which set out all schemes in development stages in the pipeline. The latest publication can be found at: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/840709/rail-network-enhancements-pipeline.pdf