Question to the Department for Transport:
To ask the Secretary of State for Transport, pursuant to the Answer of 16 June 2025 to Question 59009 on Railways: Midlands, whether the allocated funding is to support the full delivery of the West Midlands Rail Hub.
The Chancellor’s commitment to progress Midlands Rail Hub West in the 2025 Spending Review follows the release of £123 million last year to commence the design of this first phase of the scheme. Once this design work is completed, as with all schemes funded by the Rail Network Enhancement Pipeline (RNEP), moving to the delivery phase will then be subject to further investment governance and decision making.