Question to the Department for Transport:
To ask the Secretary of State for Transport, with reference to the Answer of 25 February 2015 to Question 225319, for what reasons the A483 upgrade project missed its extended deadline.
Highways England has rescheduled the scheme completion date to 28 June 2015 after further problems were uncovered during the strengthening works to the western bridge which required revised designs and approvals which had subsequent impacts on the available work areas resulting in an overall programme delay.