Ministry of Defence: Staff

(asked on 12th December 2023) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, which major projects in his Departments do not have a full time senior responsible officer.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 20th December 2023

Infrastructure and Projects Authority guidance requires all of our major programmes to have a Senior Responsible Owner (SRO) who allocates at least 50% of their time to leading their programme.

The allocation of time is based on the scope, scale, complexity and maturity of the programme and is agreed by the Chief Executive of the Infrastructure and Projects Authority, the Accounting Officer(s) and the Senior Responsible Owner.

As a result, major programmes that have been agreed as needing only a part time SRO are:

A400M

Maritime Electronic Warfare

Armour Main Battle Tank

Martlet

Ballistic Missile Defence Radar

Mechanised Infantry Vehicle

Brimstone 3

Mensa

Chinook Capability Sustainment

Meteor

Collective Training Transformation

Mine Hunting Capability

Core Production

Naval Support Integrated Global Network

Crowsnest

New Medium Helicopter

Defence Estates Optimisation

New Style of IT (Deployed)

E-7 Wedgetail

Project Bramley

European Common Radar System

Protector

Fleet Solid Support

Sea Venom

Future Combat Air

Skynet 6

Future Cruise Anti Ship

Spear Cap 3

Future Defence Infrastructure

Spearfish Upgrade

Future Materials Campus

Submarine Waterfront Infrastructure

Ground Based Air Defence

Submersible Ship Nuclear (AUKUS)

Joint Crypt Key

Teutates

Land Intelligence Surveillance Target Acquisition and Reconnaissance

Type 26

Lightning

Type 31

Reticulating Splines