Question to the Department for Energy Security & Net Zero:
To ask the Secretary of State for Energy Security and Net Zero, with reference to the Modern Industrial Strategy, what recent progress he has made in delivering the STEP prototype fusion power station in West Burton.
The STEP prototype fusion powerplant will be delivered by UK Industrial Fusion Solutions Ltd. (UKIFS), a wholly owned subsidiary of the UK Atomic Energy Authority (UKAEA), itself sponsored by DESNZ and fully owned by the UK Government. STEP will be delivered in several phases. The first has been completed producing the powerplant concept design, site selection (West Burton) and identifying the appropriate regulatory framework. Site characterisation is ongoing, and a live tender is underway to select industrial partners to work on the plant with UKIFS, and Fusion R&D Partner UKAEA.