High Speed 2 Line: Costs

(asked on 16th September 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, with reference to paragraph 2.18 of the National Audit Office report entitled High Speed Two: A progress update, published on 24 January 2020, whether HS2 Limited has updated its indicative estimate that the cost of undertakings and assurances was £1.2 billion; and in which year's prices was that estimate.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 14th October 2025

HS2 Ltd has not updated this figure. The estimate was provided to the National Audit Office in late 2019 – at that time, HS2 Ltd’s cost estimates were in 2015 prices.