Hospitals: Concrete

(asked on 10th October 2025) - View Source

Question to the Department of Health and Social Care:

To ask the Secretary of State for Health and Social Care, pursuant to the Answer of 29 January 2025 to Question 25328 on the Queen Elizabeth Hospital King's Lynn, whether he has received a copy of the report; and, with reference to his Department policy paper entitled New Hospital Programme; plan for implementation, published on 20 January 2025, what his planned timetable is for the publication of the site-by-site report of the RAAC hospitals.


Answered by
Karin Smyth Portrait
Karin Smyth
Minister of State (Department of Health and Social Care)
This question was answered on 17th October 2025

The safety of staff and patients at the seven predominantly reinforced autoclaved aerated concrete (RAAC) hospitals remains our utmost priority.

The completion date for the report has been extended to ensure a detailed understanding of the complex data and issues considered, including the RAAC condition, planned and current mitigations, and the remaining expected life of the hospital sites. By building a better understanding, we can support each scheme to move forward more effectively. We expect the report will be complete this year. A decision has not yet been taken regarding the publication of the report.

In the interim, the seven predominantly RAAC hospitals continue their programme of RAAC mitigation works and the plans for the replacement hospitals continue at pace.