High Speed 2 Line: Construction

(asked on 10th October 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what estimate (a) her Department and (b) HS2 Limited have made of the cost of construction of HS2 in each of the last five years.


Answered by
Keir Mather Portrait
Keir Mather
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 20th October 2025

Construction of HS2 Phase One started following notice to proceed in April 2020. Since October 2020, the cost to date of delivering HS2 is set out in the 6 monthly Parliamentary Report. Capital expenditure on Phase One is reported in the HS2 Ltd Annual Report and Accounts – expenditure for each of the last 5 years is summarised in the table below:

Year

Capital Expenditure on HS2 Phase One

2020/21

£3.1 billion

2021/22

£4.8 billion

2022/23

£6.6 billion

2023/24

£7.2 billion

2024/25

£6.8 billion


The Spending Review settlement has also provided £25.3 billion to progress delivery of HS2 from the West Midlands to London Euston covering financial years 2026-2027 to 2029-2030.

The programme is currently undergoing a fundamental reset under the leadership of CEO of HS2 Ltd, Mark Wild. As part of this reset, a revised cost estimate will be agreed and reported to Parliament in due course.