Motorways: Repairs and Maintenance

(asked on 24th November 2021) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether contracts have been issued for smart motorway projects on the (a) M62, (b) M40 and (c) M42 as of 24 November 2021; and what his planned timetable is for commencing that work on those motorways.


Answered by
Trudy Harrison Portrait
Trudy Harrison
This question was answered on 29th November 2021

We are currently considering the Transport Committee’s recommendations contained in its report, Rollout and safety of smart motorways, and their practical applications, and will be providing a formal response in due course.

Contracts have been previously issued for smart motorways projects on the (a) M62 Junctions 20 to 25 and the M40/M42 Interchange, which is treated as one scheme.

Early design and enabling works contracts were awarded in early 2019 for the M62 Junctions 20 to 25 and M40/M42 Interchange, with work commencing late 2019. This included detailed surveys, hard shoulder strengthening and limited site clearance. Full detailed design was awarded on 11 June 2020 followed by full construction works on 23 October 2020 through a package contract to the Smart Motorways Alliance.

Main construction works for the M62 Junctions 20 to 25 is scheduled for January 2023. Main construction works for the M40/42 Interchange commenced in October 2021 with limited vegetation clearance and ecological mitigation for communications cable diversions.