Railways: East of England

(asked on 16th October 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what progress she has made on the Ely Junction Upgrade Scheme.


Answered by
Keir Mather Portrait
Keir Mather
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 27th October 2025

The Ely Area Capacity Enhancement (EACE) programme was paused by the previous government in 2022.

The Secretary of State updated Parliament on the 7th of July on which rail and road infrastructure projects will proceed following the 2025 Spending Review.

At this stage, the EACE programme was not allocated funding. I fully recognise the strategic importance of the EACE programme. It has a strong case for future investment, and we are committed to working with stakeholders to support its place in the pipeline of future rail enhancements.