To ask the Secretary of State for Transport, what conditions for night time rail freight movements have been placed on the Oxford to Milton Keynes stretch of East West Rail.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 27th October 2025

A noise assessment for East West Rail (EWR) was undertaken for the Environmental Statement supporting the Transport and Works Act Order application for the railway. The assessment assumed a traffic flow of 8 freight trains composed of 36 wagons during the nighttime period (23:00 – 07:00). Mitigations have been provided for this in line with the Noise Insultation (Railways and Other Guided Transport Systems) Regulations.