Question to the Department for Transport:

To ask the Secretary of State for Transport, what estimate he has made of the (a) delays and (b) knock-on delays caused to Southern services at peak time due to holding trains to prevent simultaneous arrivals on platforms 15-19 at London Victoria station.


Answered by
Paul Maynard Portrait
Paul Maynard
This question was answered on 27th June 2017

It is up to the Rail Industry to deliver a timetable that provides passengers with the performance they expect, whilst maintaining safety. Peak services are timetabled to ensure there is sufficient gap between trains to allow passengers to clear platforms and concourse. Note that due to the track and platform layout at Victoria, there is a limit to the number of trains that can arrive in a short space of time at platforms 15-19.