Railways: Finance

(asked on 16th November 2022) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the financial year baseline including non-governmental costs was for the Rail Transformation Programme in 2021-22.


Answered by
Huw Merriman Portrait
Huw Merriman
This question was answered on 21st November 2022

There was no baseline for the Rail Transformation Programme pre SR 21 (and therefore in financial year 2021-22). £38.2m was spent by the Department for Transport on the programme in 2021-22, this includes the first stage of the fares, ticketing and retail reform programme, including the expansion of digital tickets.