To ask the Secretary of State for Transport, how much of the work on the Tavistock to Plymouth rail line will come from (a) existing budgets and (b) reallocated HS2 budgets in 2024.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 15th January 2024

The early development stage of the project is covered by existing budgets under the Restoring Your Railway Programme. Progression into design and delivery will use reallocated HS2 funding, subject to business case approval.