Future Combat Air System: Expenditure

(asked on 15th June 2026) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what is the total spend to date on the Tempest project, including pre-concept and early concept phases.


Answered by
Luke Pollard Portrait
Luke Pollard
Minister of State (Ministry of Defence)
This question was answered on 24th June 2026

Since its inception, the UK Government has invested over £2 billion on the Future Combat Air System (FCAS) Tempest project. In addition to this, the project has attracted over £700 million of private investment since the programme began.