To ask the Secretary of State for Transport, what estimate he has made of the (a) final cost and (b) completion date of the Midlands Rail hub.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 22nd January 2024

Network North increased the funding of Midlands Rail Hub to £1.75bn and committed to deliver the scheme in full.

MRH is being developed for delivery in two phases. The first phase, improved services between Birmingham, Bristol, Cardiff and Worcester, is currently anticipated to be operational in the early 2030s. The second phase, improved services between Birmingham and the East Midlands, is currently anticipated to be operational from the mid to late 2030s.