Question
To ask the Secretary of State for Energy and Climate Change, by what date the decommissioning of (a) Sellafield and (b) Magnox sites is planned to be complete.
The latest forecast for completion of decommissioning at the Sellafield site is 2120. The Magnox decommissioning programme is currently scheduled to be completed by 2105.