Question to the Ministry of Defence:

To ask His Majesty's Government when they will publish auditable cost records for Afghan resettlement schemes.


Answered by
Lord Coaker Portrait
Lord Coaker
Minister of State (Ministry of Defence)
This question was answered on 9th April 2026

Afghan resettlement is a cross-Government effort, with costs incurred by the Ministry of Defence (MOD) and other Government departments including the Home Office, Ministry for Housing, Communities and Local Government, and the Foreign, Commonwealth & Development Office.

On 18 March 2026, the NAO published a report which detailed the costs of the Afghan Resettlement Programme (ARP) in response to the Department’s provision of information on MOD spending to the NAO. Part Three of this report sets out funding for the schemes, the costs incurred to date, and expected future costs. This report can be accessed via the link below:

https://www.nao.org.uk/wp-content/uploads/2026/03/investigation-into-the-afghan-resettlement-schemes.pdf

The report lays out that, since 2021, His Majesty’s Government (HMG) has spent £3.1 billion on the ARP. HMG estimates a total cost of £5.5-6 billion on Afghan resettlement activity throughout the life of the programme. This figure is kept under review using the latest data available.

The MOD and its cross-Government partners will continue to update Parliament including the Audit and Risk Assurance Committee in line with usual processes throughout the course of the ARP.