Armoured Fighting Vehicles: Procurement

(asked on 6th July 2026) - View Source

Question to the Ministry of Defence:

To ask His Majesty's Government what the division of funding is between the Light Mobility Vehicle programme and the Heavy Protected Mobility programme; what is the procurement timeline for the Light Mobility Vehicle programme; and what is the planned maximum number of vehicles to be procured as part of the Light Mobility Vehicle programme.


Answered by
Lord Coaker Portrait
Lord Coaker
Minister of State (Ministry of Defence)
This question was answered on 17th July 2026

The Land Mobility Programme is a 20-year, circa £4 billion pan-Defence programme to deliver over 13,000 digitally enabled, adaptable utility and protected mobility vehicles to the Joint Force. It comprises three sub-programmes: Heavy Protected Mobility (PM), Light PM, and Light Mobility Vehicle (LMV).

The LMV programme is in its assessment phase, with competition due to start late summer 2026. The Heavy PM programme remains in its concept phase, and as a result it has not yet been assigned a funding profile. Therefore, I am unable to provide a break down in funding between the two sub-programmes until the concept phase for Heavy PM concludes.

I can, however, confirm that on current plans, LMV is due to deliver by 2030. The total number of vehicles being procured is still subject to the ongoing assessment phase.