To ask Her Majesty's Government what plans they have to accelerate the procedure for the re-opening of closed railway routes.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 6th April 2020

We have pledged £500m to reopening railway lines and stations. We invited MPs to come forward with proposals. The deadline for these proposals was 16 March. A panel comprising Ministers and rail and community experts are looking at these and we will be writing to applicants on next steps. A second round is planned for June.

Some projects, such as the Ashington Blyth line, have been accelerated and are already in development.