Nuclear Power Stations

(asked on 18th November 2022) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask His Majesty's Government when they expect new nuclear power generating capacity to come online in the UK.


Answered by
Lord Callanan Portrait
Lord Callanan
Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 2nd December 2022

The target date for commercial operations of reactor 1 at Hinkley Point C (HPC) is 1 June 2027. In order to achieve the up to 24GW deployment pathway by 2050, as set out in the British Energy Security Strategy, the Government intends to take one project to Final Investment Decision (FID) this Parliament and two projects to FID in the next Parliament, including Small Modular Reactors.

The Government is in constructive, ongoing negotiations on the Sizewell C project, which would be a replica of HPC. As announced in the Autumn Statement, subject to final approvals, the Government intends to support further development of the project, with an investment of £700m.