Question to the Department for Business, Energy and Industrial Strategy:
To ask His Majesty's Government when they expect new nuclear power generating capacity to come online in the UK.
The target date for commercial operations of reactor 1 at Hinkley Point C (HPC) is 1 June 2027. In order to achieve the up to 24GW deployment pathway by 2050, as set out in the British Energy Security Strategy, the Government intends to take one project to Final Investment Decision (FID) this Parliament and two projects to FID in the next Parliament, including Small Modular Reactors.
The Government is in constructive, ongoing negotiations on the Sizewell C project, which would be a replica of HPC. As announced in the Autumn Statement, subject to final approvals, the Government intends to support further development of the project, with an investment of £700m.