Roads: Construction

(asked on 27th January 2016) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 8 June 2015 (HL105), what trunk road improvement schemes there have been in the last five years, and for each of those, what was (1) the original target cost, and (2) the estimated completed cost.


This question was answered on 4th February 2016

The table below provides details of the major scheme on trunk roads opened in the last five financial years (from April 2011 to the present), together with the original target cost and latest outturn forecast (to the end of December 2015, and subject to closure of final accounts):

Scheme Name

Date Opened

Original Target Cost (£m)

Outturn Forecast* (£m)

A3 Hindhead

Jul-11

362.5m

371.9m

A1 Dishforth to Leeming

Mar-12

327.5m

312.0m

A46 Newark to Widmerpool

Mar-12

382.9m

379.3m

A23 Handcross to Warninglid

Oct-14

76.9m

77.9m

A11 Fiveways to Thetford

Dec-14

104.7m

99.6m

A14 Kettering Bypass

Apr-15

41.9m

37.5m

A453 Widening

Jul-15

149.7m

164.5m

Totals

1,446.1m

1,442.7m