Bats

(asked on 28th April 2016) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government what measures are used (1) to determine the cost-effectiveness of bat bridges before construction is undertaken, and (2) to determine the value of those constructed.


This question was answered on 6th May 2016

All elements of road schemes are subject to appraisal in line with Treasury requirements and guidance. They are also subject to value management requirements throughout the project lifecycle.

This does not include any specific measures on the cost-effectiveness of structures, such as bat bridges, as there is no accepted method for such quantatative evaluation. Instead a review is undertaken of the costs, qualitative benefits and other predicted impacts (including environmental) at key stages to ensure benefits are optimised and costs are challenged.