Building Safety Levy (England) Regulations 2025 Debate
Full Debate: Read Full DebateBaroness Scott of Needham Market
Main Page: Baroness Scott of Needham Market (Liberal Democrat - Life peer)Department Debates - View all Baroness Scott of Needham Market's debates with the Ministry of Housing, Communities and Local Government
(2 days ago)
Grand CommitteeMy Lords, I am grateful to the Minister for her explanation of this substantial SI. Although the formula on page 15 may have deterred the casual reader, I found the Explanatory Memorandum at the end a helpful summary of what is proposed.
I welcome the measure as it is a key part of the package proposed by the previous Government to fund remediation costs after the Grenfell tragedy. Although there is an element of rough justice here, in that developers which were not even around at the time of the Grenfell tragedy will have to pay, the alternative—the remediation costs in those cases where the developer was not remediating the building falling entirely on the taxpayer and/or the leaseholder—was even less palatable.
As the Minister said, this SI originates from the Building Safety Act 2022. At first sight, a delay of four years before it is introduced and a further delay before any money is paid are difficult to justify, given the urgent need to make progress with remediation. However, that does not matter; perhaps the Minister can confirm this. Although the taxpayer contribution is capped at £5.1 billion, the Treasury is, as I understand it, prepared to lend the department additional funds should that cap be reached; it will then recoup the money from future levies. As there is no sunset clause, the levy will remain in place until the Treasury is back in funds.
I have two main concerns about the building safety regime: the speed at which it is happening and the exemptions from the Building Safety Act. I made these criticisms of the previous Government, as noble Lords who were there may recall, and tabled amendments—unsuccessfully—to a variety of Bills. So there is nothing partisan about my remarks.
First, on speed, the department published its remediation portfolio dashboard showing the position as at the end of August this year. Of the 5,554 buildings covered by the Act—buildings are still being uncovered—35% had had their work completed and 14% had work under way. This means that, more than eight years after Grenfell, work has not actually started on over half of the buildings at risk.
The dashboard does not label this as “work not started”. Instead, there is a Whitehall euphemism describing it as “in the programme”. The next time my wife asks me why I have not unloaded the dishwasher, I will say that it is in the programme. Seriously, though, this means that thousands of people are still trapped in unsellable homes with unsafe cladding and fire safety defects, often with high service charges and high insurance—
My Lords, I apologise for interrupting the noble Lord but the House is about to divide; the Bells will ring in a moment so this would be an appropriate time to adjourn the Committee for 10 minutes.