Flooding

Henry Smith Excerpts
Wednesday 26th February 2014

(10 years, 2 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Maria Eagle Portrait Maria Eagle
- Hansard - - - Excerpts

I will say a little about climate change later in my remarks, but the hon. Lady has certainly made her point.

After the Prime Minister became involved, one by one the measures that had been resisted for weeks have finally been announced: vital assistance from the armed forces; funding to help households, businesses and farms, although much of the detail needs to be clarified; council tax exemptions, after my right hon. Friend the Leader of the Opposition forced a welcome U-turn; and a hastily convened meeting with the insurance industry, although it is far from clear what that meeting has delivered in terms of faster payouts. Those measures should have been put in place when the water levels first rose, at the end of last year.

A great many questions still need to be answered about the assistance that is available. For example, the Business Secretary has suggested that VAT on flood repairs should be reduced. Perhaps the Communities Secretary can clarify matters and say whether that suggestion is now Government policy, or was it just being floated as part of the Liberal Democrats’ so-called differentiation strategy?

After the floods of 2007, half of those who were forced to leave their homes were back in them within six months, yet many of those people had to wait much longer for the money needed to sort out the damage. I hope that the Communities Secretary will update the House on what discussions with the insurance industry have led to. In particular, can he say whether the Government agree with the proposal by my right hon. Friend the Leader of the Opposition for a new industry standard, because taking 12 months to complete a claim seems far too long?

There is still a lack of clarity on the time scale for restoring the rail link between Exeter and Newton Abbot, following the collapse at Dawlish. Initially, it was claimed that the work could be completed within six weeks, but now we are told that the line may not reopen until mid-April. With up to £20 million a day being lost by businesses, I hope that the Communities Secretary will provide an update on efforts to achieve an earlier reopening of this vital transport link.

We have heard nothing from Ministers on what specific steps the Department for Environment, Food and Rural Affairs is taking to help our fishing fleets, particularly in the south-west. Many fishermen have been unable to work since Christmas and consequently now face a desperate financial crisis. After two months of no fishing, damaged boats and lost equipment, the Communities Secretary will, I hope, provide some clarity on what help will be available to that vital British industry.

There are growing concerns about the impact on the tourism industry, which is vital for the economy of the south-west in particular. It is reported that a quarter of all tourism operators have experienced cancellations, and 40% have seen fewer forward bookings during a vital period for organising summer breaks. I hope that the Secretary of State, or the Minister who is responding to the debate, can set out what the Government have done to ensure that people are aware that all parts of Britain are open for business.

Ministers continue to be silent about whether or not an application is to be made to the European Union solidarity fund. After the 2007 floods, the previous Government successfully secured £110 million as a contribution to the cost of recovery. After the UK special abatement mechanism, the net value is £31 million. Considering that that is more than the total extra money announced for this year, it is surprising that securing that funding does not appear to be a priority. I hope that the Secretary of State can assure the House that some kind of anti-EU political dogma is not standing in the way. We look forward to hearing what he can tell us about what is going on.

The Government were caught sleeping on the job when the severe weather first hit the country in December, but the roots of this failure go back to the ill-judged decision made by the Government after the 2010 election significantly to reduce the funding available for flood protection. The budget of the Department for Environment, Food and Rural Affairs had to be cut, but it is a question of what the priorities ought to be. A decision was made to target the flood defences budget, despite all the evidence that investing in flood defences saves more than it costs.

Maria Eagle Portrait Maria Eagle
- Hansard - - - Excerpts

I will not give way. I have given way on a number of occasions, and I want to make progress.

This reckless short-termism is set to cost the country more than the cuts were intended to save. The Pitt review commissioned by Labour after the 2007 floods made it clear that investment in flood protection needed to rise, and by time of the 2010-11 Budget set by Labour, funding had gone up from £500 million a year to £670.1 million, yet by 2011-12, in the first Budget set by the coalition Government, that had been cut to £573 million, which is a reduction of £97 million—a 17% real-terms cut.

--- Later in debate ---
Maria Eagle Portrait Maria Eagle
- Hansard - - - Excerpts

The reductions to flood defence spending were not just numbers on a spreadsheet, but actual planned flood defence projects.

Henry Smith Portrait Henry Smith
- Hansard - -

Will the hon. Lady give way?

Maria Eagle Portrait Maria Eagle
- Hansard - - - Excerpts

No, not at this time. [Interruption.] I have given way relatively generously, so I do not think I should be criticised for saying no on one occasion.

In total, 290 shovel-ready flood defence projects were cancelled and 966 delayed as a result of those decisions. Appallingly, these appear to have included 13 schemes along the Thames and 67 in the south-west. Does not that highlight the cost of the Government’s misguided approach? The Secretary of State for Environment, Food and Rural Affairs also cut more than 40% from his Department’s budget for domestic climate change initiatives last year. Therefore, just 0.7% or £17.2million of the Environment Department’s budget is now dedicated to preparing or adapting Britain for the impact of climate change, and his is the lead Department. Of course, we only know this thanks to an freedom of information request, because the Secretary of State sought to disguise the cut by lumping it in with the funding to meet our obligations to the international climate fund.

Before these floods hit, Ministers were about to make yet another ill thought through decision that would have reduced the country’s ability to cope with major flood incidents. In addition to the 600 Environment Agency staff lost since 2010, we know from leaked briefings that a further 557 flooding staff were due to be cut this year. The Prime Minister has said that

“those aren’t plans that are going to be put in place”.

Yet it is far from clear whether this means that there will be no further job losses in the agency, or whether the commitment relates only to those working directly on flood protection. Neither is it clear for how long this commitment remains valid. I hope that the Secretary of State will clarify the situation and give us some further information on this.

There have been some disgraceful attempts by Ministers to place the blame for some of these decisions at the door of the Environment Agency, not least by the Communities Secretary himself. Yet, as the chairman of the Environment Agency has made clear,

“a limit on the amount we can contribute to any individual scheme, determined by a benefit-to-cost rule imposed on us by the Treasury”

was placed on the agency.

I hope that the Communities Secretary will take the opportunity to confirm that the cost-benefit ratio rules imposed on flood defence schemes will be reviewed. I hope that he will also accept, in hindsight, that Ministers should not have sought to evade responsibility for their own decisions.

The Pitt review set out 92 separate recommendations, all but one for the Government, and significant progress on their implementation was being made at the time of the last election, yet when this Government came to office in 2010, some recommendations that had been implemented were reversed. The Cabinet committee on improving the country’s ability to deal with flooding and the national resilience forum were both abolished. Then in January 2012, the Government published what was entitled a “final progress report”, despite 46 recommendations not having been fully implemented. We urgently need clarity on the progress—or lack of it—that has been made since January 2012. I hope that the Secretary of State will reconsider his previous refusal to agree to our call for a new update to be brought before Parliament.

The Government have demonstrated a complete lack of urgency in securing the legal basis for the proposed flood reinsurance scheme. Thanks to three years of inaction from Ministers, this scheme will not be in place until 2015 at the earliest. As we have warned throughout the passage of the Water Bill, which is still being considered in another place, the scheme is deeply flawed. In Committee, Conservative and Liberal Democrat Members of this House voted down Labour amendments to improve the Bill. Those amendments included requiring Ministers to consult the Committee on Climate Change on the number of properties that might need to be added to the scheme in future; incentivising owners of at-risk properties to invest in flood protection measures; enabling people to search whether or not a property is included in the scheme; and establishing an appeal mechanism for those excluded—all measures opposed by the Government.

A balance has to be struck, of course, between the cost of the levy on other households and the scope of the scheme. However, the significant number of exemptions from the scheme continues to be of real concern and controversy, not least for tenants and leaseholders. In the light of the recent floods and the fact that the Water Bill has not completed its passage through both Houses, I hope that the Minister might consider agreeing to cross-party talks on those issues. It is vital that we ensure that the Flood Re insurance scheme is fit for purpose over the long term.

--- Later in debate ---
Lord Pickles Portrait Mr Pickles
- Hansard - - - Excerpts

I am very grateful to my hon. Friend, who makes some reasonable points and shows what can be done. In fairness, the weather was much worse for a more prolonged period than it was in 2007, and the number of dwellings affected is 7,000 or thereabouts, which is just a tiny proportion of the 55,000 or 56,000. That is a reflection of some very good protection work.

Henry Smith Portrait Henry Smith
- Hansard - -

Will my right hon. Friend also welcome the £11.7 million that has been spent on the upper River Mole flood alleviation scheme since 2010, which has protected hundreds of homes that otherwise may have been flooded during recent events?

Lord Pickles Portrait Mr Pickles
- Hansard - - - Excerpts

My hon. Friend makes a reasonable point.