Railways: East Coast Main Line

Lord Rosser Excerpts
Tuesday 30th October 2018

(5 years, 5 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Baroness Sugg Portrait Baroness Sugg
- Hansard - - - Excerpts

My Lords, I am afraid that I am not able to give a definite date. We are trying to introduce the trains as soon as possible, but there remain issues that we need to work through. LNER has said that it hopes to start introducing the trains early next year. On my noble friend’s point about King’s Cross, we are carrying out essential works on King’s Cross to replace the expired track and signalling to ensure that we can see the full benefits of the east coast main line enhancements.

Lord Rosser Portrait Lord Rosser (Lab)
- Hansard - -

It was from the government Dispatch Box that we were told on 23 May this year that:

“The good news also is that we fully expect the new intercity express trains to be introduced on the east coast main line from the end of this year, as planned”.—[Official Report, 23/5/18; col. 1032.]


Is this episode yet another example of the reality that, in our fragmented railway system, no one is in overall charge? No one is ultimately accountable for the performance or lack of it of our national railway network and, as a result, no one accepted responsibility for ensuring that the new trains would start running on the planned date. If the Government disagree that that is the case, then which individual or body was accountable for ensuring that the new trains would start running on the planned date on the east coast main line?

Baroness Sugg Portrait Baroness Sugg
- Hansard - - - Excerpts

Well, that was not me. The noble Lord is quite right to say that in May I gave reassurance that those trains would come into service. At the time, that was very much what we were planning. However, as I said, there have been emerging issues on that which we need to work through. It is not unusual with delivery of a whole new infrastructure—and this is a £2.7 billion investment, which we should welcome—that there are some compatibility issues. We are working through them. On the noble Lord’s point about the rail system, it has been well over a decade since we have seen a large change in the rail network and, while we have seen record private investment and the doubling of passenger journeys, of course it has had its challenges. The time is absolutely right for a comprehensive review, and that is what the rail review will do.