Wednesday 25th March 2015

(9 years, 1 month ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Cheryl Gillan Portrait Mrs Gillan
- Hansard - - - Excerpts

There is a lot of support for that on this side of the House. I do not want a Labour-led Government, and certainly not one that will be blackmailed by a smaller party. I want an incoming Conservative Government with a healthy majority to rethink, refine and re-engineer this project before we are locked into the most expensive Procrustean bed in history.

I turn to some of the detail and the increasing problems. On the current plans for HS2 phase 1, there is still no confirmed connection to central London. The Euston proposals have gone back to the drawing board and Old Oak Common just might be the final terminus. That will connect with nowhere meaningful for many years.

Michael Fabricant Portrait Michael Fabricant (Lichfield) (Con)
- Hansard - -

My right hon. Friend has been a good friend since 1992 and a doughty fighter on this particular campaign. On the point that she just made, is she also aware that many people in the midlands, while having to put up with HS2 crashing through their constituencies and countryside, were at least offered the chance of going to a railway station, say, in Birmingham in the morning and waking up in the afternoon in Paris or Lille? However, not only does it not connect with London in the way in which we thought, but it does not even connect with the channel tunnel.

Cheryl Gillan Portrait Mrs Gillan
- Hansard - - - Excerpts

That is absolutely correct. There is no direct connection to the channel tunnel, and people, particularly up in the north, have been sold a pup; they were told that they could get to Brussels or the continent much more easily, but that is not going to happen. Also, until we know the outcome of the Davies commission on airports, no connection to any future hub airport in the south-east will exist, and even the Heathrow link or spur has been cancelled. That might gladden the heart of my right hon. and learned Friend the Member for Beaconsfield (Mr Grieve), for whom I have a great deal of sympathy, but the fact is that the project is being developed in isolation.

--- Later in debate ---
Cheryl Gillan Portrait Mrs Gillan
- Hansard - - - Excerpts

I suppose I could say that they are lucky they have no disbenefit from HS2, but that is one of the pertinent points. This railway is being built for the few, certainly not the many.

Even the claims of rebalancing the economy between the north and the south do not stack up. There is clear evidence pointing to London being the real gainer from the project as currently configured, and we are all forgetting the ill fated KPMG report that revealed that many parts of the country would lose millions of pounds from their local economies, because those economies would be hollowed out as businesses were attracted, like a bee to a honeypot, to the line of route.

I am sad to say this to my hon. Friend the Minister, whom I consider to be a friend and of whom I am very fond, but—[Laughter.] There is always a “but” with me. This project has been guilty of unsatisfactory and often callous public engagement with the people and communities affected, disrespect for opposing viewpoints, including those of elected representatives, failure to observe the basic rules of consultation, often perceived indifference towards the environment, and suppression of the reports on the deliverability of and risks posed by the project.

Cheryl Gillan Portrait Mrs Gillan
- Hansard - - - Excerpts

That is not a great track record, if hon. Members will forgive the pun. I will certainly give way now that I have delivered my punchline.

Michael Fabricant Portrait Michael Fabricant
- Hansard - -

My right hon. Friend is very kind and very generous; she knows me of old. Is it not interesting that one reason why the present Government decided not to go with the original Arup proposal and follow the route, which would have been much cheaper, of an existing transport corridor was that they wanted to go at ultra-high speed, and ultra-high speed trains need to travel in straight lines? However, because of the work of the Department for Transport and the ongoing work of the parliamentary Committee, which has caused a number of changes in the route, we now know that in fact the trains will not be able to go at ultra-high speed, because there are so many changes to the route. They could have followed an existing transport corridor, saving money and the environment.

Cheryl Gillan Portrait Mrs Gillan
- Hansard - - - Excerpts

That is a very valid point, but I have to say that, following the publication of a recent document, we know that HS2 will at least be well designed. The latest document from HS2 is “HS2 Design Vision”. It is not a very weighty document, but there is a long list of contributors, and I learn in it that we will be

“Celebrating the local within a coherent national narrative”.

It continues:

“Each place and space that is created as part of the system will contribute to HS2’s own identity.

The design challenge will be to develop a coherent approach, establishing uniformity where it is essential while encouraging one-off expression based on local context where appropriate. HS2 seeks to enhance national and civic pride, while also supporting its own brand to support its operational and commercial objectives. It will therefore include many local design stories within one compelling national narrative.”

I am a fellow of the Chartered Institute of Marketing and an old marketing director, and that takes even my breath away. I have to say that it is not worth the paper it is written on. My hon. Friend the Member for Lichfield (Michael Fabricant) is quite right. The design of the project is coming into question, because there were alternatives that have not, in my view, been properly considered. After six years of the project, since Andrew Adonis first announced it, we were supposed to have a fully integrated, connected railway smoothing northern access to the continent, whisking non-train-working businessmen along at speeds hitherto only dreamed of on a British railway and reducing air travel demand. We learn from recent press coverage that those passengers will be whisked along on luxury leather-upholstered seating in child and family-free carriages. The design vision has, for me, really put the icing on the cake. Is this really what people want? Certainly not the people who have contacted me, not only from my constituency but from up and down the country.

The list of detractors grows daily. In addition to the Lords report published today, we can count the Environmental Audit Committee, the National Audit Office, the Public Accounts Committee, the Institute of Directors, and numerous local authorities and outside commentators. Last week, I wrote to the chairman of the Office for Budget Responsibility to ask him, as part of his remit to assess the long-term sustainability of the public finances, to carry out a review of the impact of HS2 on budgeted capital expenditure and Department for Transport expenditure. Should I be fortunate enough to be returned to the House by the electors of Chesham and Amersham after 7 May, I hope that I will receive a detailed response from Mr Chote that may enlighten us more.

Many detailed questions are posed in the Lords report, all of which need to be answered before the project goes any further. I think that the Minister should consider some specifics, particularly if he is willing to rethink the project. The rebalancing of wealth between north and south is an admirable objective. With a family who came from a steel firm in Sheffield, I know that better than most, as do you, Mr Betts. However, would it not yield faster and more effective results, as I have often said, if cross-Pennine connections were prioritised before any London-Birmingham link? Before starting on any link from Birmingham southwards, should we not wait for the Davies report on airport capacity in the south-east and plan accordingly? More importantly, should we not commission a major strategic transport plan across all modes of transport, with particular reference to the modern and emerging technologies of smart motorways, driverless cars, driverless trains, super-Maglev and vacuum tube trains, to say nothing of the increasing power and use of high-speed broadband and satellite communications, which were raised by the Prime Minister today in a tremendous Prime Minister’s Question Time?

We in the line of the route have always had to make other plans. We could not simply oppose the project; we had to make contingency plans in case it went ahead. In this day and age of politicians outbidding each other to be greener than green, how can we plan for HS2 to destroy parts of 41 ancient woods and damage a further 42 that lie near the construction boundary, to say nothing of the destruction of the area of outstanding natural beauty and the historic sites that lie in the path of the monster?

Convinced, if the project goes ahead, that the destruction of the area of outstanding natural beauty in the Chilterns can be avoided—and with my support, and that of my right hon. Friend the Member for Aylesbury (Mr Lidington), the right hon. Member for Buckingham (John Bercow), my right hon. and learned Friend the Member for Beaconsfield and particularly my hon. Friend the Member for Wycombe—Chiltern district council, Buckinghamshire county council, the Chilterns conservation board and Aylesbury Vale district council commissioned a new, independent report to consider a better and viable alternative to the Government’s route through Buckinghamshire. The report will be published tomorrow and presented here, in Committee Room 19, at 4 o’clock, and I invite the Minister and other hon. Members to attend.

The main conclusion of that study is that a long tunnel for the transit of the Chilterns by HS2 is technically feasible and would protect the designated landscape of the Chilterns AONB and the green belt. The second conclusion is that that would offer a better alignment. The details have already been shared with HS2 Ltd to give it time to consider the study before the local authorities appear before the Select Committee, and I commend the report to the House. Accepting that option would save time and money, because such environmental protection would reduce the number of petitioners, lawyers’ fees and the time that people spend scrutinising the legislation. It would avoid some of the last-minute, knife-edge decisions that are being forced on people before they give evidence to the Select Committee. Giving evidence to a Select Committee is a daunting prospect even for a politician. It is really daunting for a layman who has an emotional investment in the proceedings, and who risks losing their home and habitat.

We should also question whether we should let HS2 Ltd continue to spend and enter long and expensive contracts when the project has not yet cleared all its parliamentary and political hurdles. The questions that I have had answered recently leave no doubt about the fact that HS2 Ltd is recruiting more and more people on higher and higher salaries. According to reports in the press, some 18 executives are paid more than the Prime Minister. I do not know whether that is true; I do not believe everything that I read in the press. However, it is alarming to think that such highly paid people are contracting on a regular basis—I have a list of the contracts—when they have not been given the clear say-so by this House or the other place.

I believe more than ever that a pause and a re-evaluation are necessary before the die is cast and we have no option but to plough ahead. I will conclude shortly, because I know that many other people want to speak. I hope that the Members who are allowed to speak will be those along the route who have a real interest in the matter because their constituencies will be particularly affected. I hope that the speakers will not simply be, as always seems to be the case, those who habitually support the project from afar. Before I conclude, I want to raise some compensation matters, because we have all had to make plans on the basis that the project would go ahead. As many hon. Members know, the lives, properties, businesses and futures of many of our constituents have been blighted by this project. They have lived through five years of sheer hell, or, as I have dubbed it, shire hell. Some—the lucky ones—have sold, and they have usually accepted offers of less than their properties are actually worth. Some have moved on. Some have had their health severely affected. Some have died. Some have taken the compensation on offer.

It was only this year, after five years, that the compensation for my constituents and “the need to sell” scheme were finally settled. People are still battling with complex bureaucracy, form-filling and unacceptable questioning. I have the distinct impression that lifestyle judgments are being made about people who apply for compensation. It should be none of the Department’s business what lifestyle anyone chooses to pursue. The decision should not really depend on what other assets they have, because it is the asset in question—usually their home—that is affected. The Department should accept the need to sell without making onerous demands for personal details.

--- Later in debate ---
Frank Dobson Portrait Frank Dobson (Holborn and St Pancras) (Lab)
- Hansard - - - Excerpts

I thank my right hon. Friend the Member for Chesham and Amersham (Mrs Gillan) for her kind remarks about our co-operation and for thanking the various bodies concerned.

Today’s report from the House of Lords Economic Affairs Committee batters great lumps out of the case for HS2. The Committee did not ask any questions that we have not been asking for the last five years. HS2 had no satisfactory answers before, and it apparently still has none.

I want to draw attention to the situation in my constituency, which is the most affected by the proposals. The proposals involve the demolition of the homes of about 500 people and would leave about 5,000 people living next to Europe’s biggest building site for the best part of 15 years.

Under the original proposals, HS2 was going to knock down Euston station and rebuild it, incorporating a further 75 metres to the west to provide space for everything, including the new high-speed line. Originally, that was going to cost £1.2 billion. Eight months later, a revised estimate of £2 billion was put forward—the figure had gone up by just £100 million a month. Apparently, £2 billion was too much, so the scheme was cut back, which would have given us a rather elegant lean-to shed for HS2 at the west side of Euston station, at a cost of £1.4 billion. That is what was in the Bill that came to the House of Commons. By the time it got here, however, we were told that that was not going to be done any more and that we would go back to the vast new scheme. The detailed proposals for that scheme were supposed to be available in October last year. Recently, in meetings with local people, however, HS2 has admitted that it has no such proposals and that it is going back to the lean-to shed version, which will now cost £2.6 billion. Who would put £50 billion on a racing stable that produces rubbish like this?

We were told that a supposed connection to the channel tunnel link would bring all sorts of benefits: people would be able to get on a train in Manchester and go to Paris. We told HS2 that that was not a workable proposition, and even the Institution of Civil Engineers said it was not, but no, HS2 persisted—and then the connection was abandoned. One explanation was that HS2 had come across “unforeseen factors”, including the need to “widen the route”. Now, anybody who starts an engineering project without realising that they will need to widen the route if they add some lines really is not fit to be put in charge of spending £50 billion.

Michael Fabricant Portrait Michael Fabricant
- Hansard - -

Is my right hon. Friend—I will call him that—aware that the completion of Birmingham New Street, including a new department store, has been delayed by a year and a half because of construction problems? Who is doing the project? The selfsame people who are supposed to be designing the new Euston HS2 terminal.

Frank Dobson Portrait Frank Dobson
- Hansard - - - Excerpts

I should add, Mr Betts, that the people who have been making those preposterous estimates, coming up with ludicrous proposals that will not work, are all very well-rewarded consultants. I believe that they have already had three quarters of a billion pounds in fees, so hard-working consultants are doing rather well. As far as I can see, the only train that has actually moved is the consultancy gravy train.

I advise people that if we want to benefit the cities of the north, the answer is to invest in the cities of the north and their immediate transport requirements, rather than spending what it is now believed will be £7 billion on a full-scale development of Euston. Will Sheffield, Leeds or Manchester benefit from an investment of £7 billion in Euston? Euston certainly will not benefit, and I do not think anywhere else will.

--- Later in debate ---
Kelvin Hopkins Portrait Kelvin Hopkins (Luton North) (Lab)
- Hansard - - - Excerpts

It is a pleasure to serve under your chairmanship, Mr Betts, and to follow the right hon. Member for Chesham and Amersham (Mrs Gillan). I have spoken on HS2 on previous occasions in the House and I remain of the view—in fact, it has got stronger—that is wholly unnecessary and ridiculously expensive. The figure of £50 billion is talked about quite a bit, but Hansard on 5 March shows that my hon. Friend the Member for Huddersfield (Mr Sheerman) drew attention to evidence presented to the HS2 Committee that

“hidden costs will raise the overall cost of the HS2…to £138 billion”. —[Official Report, 5 March 2015; Vol. 593, c. 1062.]

That is a massively higher figure. My contacts in the industry suggest that that figure is perfectly justifiable and some say that the real figure would be even more.

Even if things are expensive, I would still support them if they are the right thing to do, but this project is not. I made a written submission to the House of Lords Committee to set out my views in more detail, which is available on the internet. I have spoken on them before, but let us get the first nonsense of HS2 out of the way first of all: that must be Euston. It is the wrong station in the wrong place. The last place that a business traveller from Birmingham or whatever who wants to get to the City or Canary Wharf wants to arrive is Euston. They would want to get to somewhere linked on to Crossrail to get through to those places, and not have to struggle with their laptop and wheelie case from Euston on to the tube and then the docklands light railway to get to Canary Wharf. That is a nonsense.

Michael Fabricant Portrait Michael Fabricant
- Hansard - -

The right hon. Gentleman is absolutely right. Is he also aware that a business traveller from the Birmingham area first has to get to Birmingham New Street and then, with all their baggage, has to walk across Birmingham to get to Curzon Street station, only to end up at the wrong station—Euston? As I said earlier on, any hope of getting directly to France has now evaporated.

Kelvin Hopkins Portrait Kelvin Hopkins
- Hansard - - - Excerpts

I am not yet a Privy Counsellor and I do not suppose that I ever will be, but the hon. Gentleman’s point about Curzon Street was absolutely right; I was coming to it myself. In my submission to the House of Lords Committee, which was titled, “Sensible alternatives to HS2”, I gave three specific alternatives that would cost a fraction of that amount but solve all the problems that HS2 might supposedly solve.

First, I suggested the electrification of the Birmingham Snow Hill line, via Banbury, to London. It currently goes to Marylebone or Paddington, but it could easily be linked—the tracks are already there, so all it needs is a bit of track work—to Crossrail going in both directions. If we had an electric train from Snow Hill in the middle of the Birmingham business district that went direct to Canary Wharf at 125 mph, someone could work on a laptop without changing trains and I bet that train would beat HS2 if otherwise that person had to get to Curzon Street and then get two tube trains at the London end. HS2 is a complete and total nonsense, but that suggestion would provide wonderful extra capacity.

That would also allow travel direct to Heathrow from the centre of Birmingham and it could be linked through from Leamington Spa on to the west coast main line, so we could have Birmingham airport linked to Heathrow airport with a direct, 125 mph, one-hour service. They could almost be hubs or satellites for each other. There could be trains from further north—from Manchester—coming down the west coast main line, joining the Banbury line and going directly from the centre of Manchester to Heathrow or Canary Wharf. It is possible for a tiny fraction of the cost of HS2.