Written Question
Renewable Energy: Community Development
Wednesday 27th March 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, with reference to the oral contribution of the Parliamentary Under-Secretary of State for Energy Security and Net Zero during Consideration of Lords message on the Energy Bill [Lords] on 18 October 2023, Official Report, column 352, when she plans to publish the consultation on barriers to developing community energy projects.

Answered by Graham Stuart

We have been codesigning the consultation on the barriers to community energy schemes with the Community Energy Contact Group. We intend to publish the consultation as soon as possible.


Written Question
Electricity Generation: Renewable Energy
Tuesday 20th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy, Security and Net Zero, when she will launch a consultation on removing the barriers to selling clean electricity.

Answered by Graham Stuart

The Government has announced that it will consult on the barriers preventing the development of community energy schemes. The Government is actively working with the Community Energy Contact Group on the content of the consultation and plans to publish the consultation as soon as possible once these discussions have concluded.


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what recent estimate she has made of the annual operating expenditure of a 1GW hydrogen-fired power plant commissioned in 2030.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

The Electricity generation costs 2023 report published by the Department for Energy Security and Net Zero sets out the assumptions for a hydrogen-fired Combined Cycle Hydrogen Turbine power plant commissioned in 2030.

Hydrogen to Power is an emerging technology and as such all figures are subject to change. We will continue to monitor and update cost estimates based on new evidence as it becomes available.

https://www.gov.uk/government/publications/electricity-generation-costs-2023


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what recent estimate she has made of the operating expenditure cost of generating one tonne of green hydrogen in a plant commissioning by 2030.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

‘Hydrogen Production Costs 2021’, published by the Department for Business, Energy and Industrial Strategy in August 2021, sets out the levelised cost of various hydrogen production technologies. Please see:

https://www.gov.uk/government/publications/hydrogen-production-costs-2021

We will continue to monitor and update cost estimates based on new evidence as it becomes available.


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department's latest estimate is of the capital expenditure cost of a new 1GW hydrogen-fired power plant commissioning by 2030.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

Figures published by the Department for Energy Security and Net Zero in the Electricity generation costs 2023 report estimate that a 1.2 GW Combined Cycle Hydrogen Turbine (CCHTs) would cost £830million in 2025 to construct, falling to £740million by 2040.

Hydrogen to Power is an emerging technology and as such all figures are subject to change. We will continue to monitor and update cost estimates based on new evidence as it becomes available.

https://www.gov.uk/government/publications/electricity-generation-costs-2023


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what recent estimate she has made of the mass of hydrogen required to be burned in a hydrogen-fired power plant to generate 1GWh of electricity.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

Figures published by the Department for Business, Energy and Industrial Strategy in the June 2022 Hydrogen Readiness Report suggest that an 800MWh hydrogen-fired power plant would require 50 tonnes of hydrogen fuel per hour. Therefore, a 1GWh plant could be expected to require 62.5 tonnes of hydrogen.

https://www.gov.uk/government/publications/electricity-generation-costs-2023


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department's latest estimate is of the mass of hydrogen that would be produced per running hour by a 1GW blue hydrogen plant.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

A 1GW[1] blue hydrogen production plant running for 1 hour at full capacity would produce 1GWh of hydrogen, equivalent to 25.4 tons.

[1] Rated as 1GW on the basis that the hydrogen it produces will be used for combustion and the latent heat of vaporisation of water is recovered


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department's latest estimate is of the capital expenditure cost of a new 1GW green hydrogen plant commissioning by 2030.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

‘Hydrogen Production Costs 2021’, published by the Department for Business, Energy and Industrial Strategy in August 2021, sets out the levelised cost, based on commissioning year, of various hydrogen production technologies. The information requested can be found in the table ‘Technical and cost assumptions (2020 real prices) within the annex to the report. The capital expenditure associated with a 1GW electrolytic plant commissioning in 2030 ranges from £433 million to £1,708 million depending on the technology. Please see:

https://www.gov.uk/government/publications/hydrogen-production-costs-2021

We will continue to monitor and update cost estimates based on new evidence as it becomes available.


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what her Department's latest estimate is of the capital expenditure cost of a new 1GW blue hydrogen plant commissioning by 2030.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

‘Hydrogen Production Costs 2021’, published by the Department for Business, Energy and Industrial Strategy in August 2021, sets out the levelised cost of various hydrogen production technologies. The information requested can be found in the table ‘Technical and cost assumptions (2020 real prices) within the annex to the report. Therefore, the cost from the table is £531 /kW hydrogen HHV meaning £531M for the 1GW plant.

Please see: https://www.gov.uk/government/publications/hydrogen-production-costs-2021

We will continue to monitor and update cost estimates based on new evidence as it becomes available.


Written Question
Power Stations: Hydrogen
Tuesday 13th February 2024

Asked by: Selaine Saxby (Conservative - North Devon)

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what recent estimate her Department has made of the operating expenditure cost of generating one tonne of blue hydrogen in a plant commissioning by 2030.

Answered by Andrew Bowie - Parliamentary Under Secretary of State (Department for Energy Security and Net Zero)

'Hydrogen Production Costs 2021’, published by the Department for Business, Energy and Industrial Strategy in August 2021, sets out the levelised cost of various hydrogen production technologies. The annex to the report (worksheet '2030_R') sets out a range of levelised costs for gas reformation with CCUS (blue) hydrogen production commissioning in 2030. Costs range from 1,454 to 3,096 £/tonne hydrogen depending on technology [1]. Please see:

https://www.gov.uk/government/publications/hydrogen-production-costs-2021

We will continue to monitor and update cost estimates based on new evidence as it becomes available.

[1] Costs are calculated on the basis that the hydrogen is used for combustion and the latent heat of vaporisation of water is recovered.