Type 26 Frigates: Clyde Debate

Full Debate: Read Full Debate
Department: Ministry of Defence
Tuesday 18th October 2016

(7 years, 6 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Wayne David Portrait Wayne David (Caerphilly) (Lab)
- Hansard - -

It is a pleasure to serve under your chairmanship, Mr Hollobone. It has been said that confusion and muddle have been the hallmark of the Government’s approach towards naval shipbuilding in recent years. Nowhere is that lack of clarity more in evidence than when it comes to the construction of frigates.

The Navy has 13 Type 23 frigates. As we have heard, there was a strong suggestion in the 2010 strategic defence and security review that 13 Type 26 frigates should be constructed in place of those 13 Type 23 frigates. We were told that manufacturing of those new frigates would begin in 2015-16, but the 2015 SDSR cut the number from 13 to eight. At that time, the Government gave a weak commitment to building at least five new general purpose frigates, possibly more. They have yet to agree a manufacturing date with BAE Systems for the Type 26 frigates, and the demonstration phase on those frigates was extended in March 2016 by a further year. At the same time, BAE Systems has been building three offshore patrol vessels, and the Government plan to have two more of those. That general factual background leads to a number of key questions that have been touched on in the debate, and that I want to underline.

First, with regard to timescale, if the Government do not give the go-ahead and the date for the cutting of steel is not before summer next year, the production trades will have almost finished manufacturing work on those offshore patrol vessel programmes, and will have no work to carry on with. In other words, there will be a hiatus. The trade skills that are required for the construction of the offshore patrol vessels will be lost and will not be able to be deployed other than at significant cost, with more delays and more training. It is important that the Government come clean; they must have some idea of the start date, and I hope that the Minister will tell us when that will be.

The second question is again on the issue of skills and the dovetailing that will be necessary between the Type 26 programme and the programme for the general purpose frigates. The trade unions have pointed out that as the Type 26 programme design phase is decreasing, the ship designers will need another programme to work on, so we need specifics from the Government on the general purpose frigate programme as well. What is the Government’s intention in that regard?

Thirdly, we have already seen delay—hopefully there will not be more—but what does that mean for the existing Type 23 frigates? The Government have said that there is to be no extension of their lifespan. Is that still the case? I have been told that the Type 23 frigates have already exceeded their original design life. If they are kept in service, there are implications for the Navy, in terms of fulfilling the requirements that those frigates meet.

The final question is on cost, and clarity would be desirable here. As we have heard, there have been suggestions that because of the Government’s continuing austerity programme and the hardening of cuts, it is becoming increasingly expensive for them to make real their previous commitments. Admiral Sir Philip Jones, the First Sea Lord and head of the Navy, suggested that when he told MPs on the Select Committee that one problem is the cost of designing quiet ships; the technology is far more expensive than was originally envisaged. That may or may not be the case, but what is very important, on that and on the other issues raised this afternoon, is that we have clarity and certainty from the Government.

Chris Stephens Portrait Chris Stephens
- Hansard - - - Excerpts

Does the hon. Gentleman agree that delays have an economic impact, and not just on Govan, Scotstoun or Scotland? There is a wider economic impact. If there is a delay, that will mean a more expensive programme in the long run.

Wayne David Portrait Wayne David
- Hansard - -

Broadly speaking, that is correct. There will certainly be excessive costs if the Type 23 frigates are required to stay in service beyond their natural design life. Also, with most programmes, and certainly with defence procurement programmes, the longer the programmes, the more the delay and the greater the costs. There is also an impact on the workforce, with greater uncertainty and greater job insecurity. On all these issues, what is required is, at the very least, clarity from the Government. I thank the hon. Member for West Dunbartonshire (Martin Docherty-Hughes) very much for bringing forward this issue today.

Harriett Baldwin Portrait The Parliamentary Under-Secretary of State for Defence (Harriett Baldwin)
- Hansard - - - Excerpts

Let me start by saying what a pleasure it is to serve under your chairmanship this afternoon, Mr Hollobone. I congratulate the hon. Member for West Dunbartonshire (Martin Docherty-Hughes) on securing this debate and for providing me with the opportunity to update the House on this important subject.

The 2015 strategic defence and security review restated this Government’s commitment to the Type 26 global combat ship programme. It was a positive strategic defence and security review for the Royal Navy, committing to an increase in the size of the service for the first time in a generation.

There has been a high level of interest in the programme since we announced our plans and I, along with ministerial colleagues, have consistently confirmed the Government’s continuing commitment to it. Let me once again reiterate that commitment. The Type 26 global combat ships remain critical for the Royal Navy and nothing has changed since last year’s strategic defence and security review. We are going ahead with eight anti-submarine warfare ships and all eight ships will be built at the BAE Systems shipyards on the Clyde.

We have backed up our commitment with significant investment as we continue to progress the Type 26 programme. We announced in March this year the award of a contract with BAE Systems, valued at £472 million, to extend the Type 26 demonstration phase to June 2017, enabling us to continue work with industry to develop an optimised schedule for the programme to reflect the outcome of the strategic defence and security review; to mature further the detailed ship design ahead of the start of manufacture; to invest in shore testing facilities; and to extend our investment in the wider supply chain to cover almost all the equipment for the first three ships.

Wayne David Portrait Wayne David
- Hansard - -

I welcome what the Minister has said, but it is worth pointing out that so far there is nothing new in it. Will she tell us when the manufacturing start date will be?

Harriett Baldwin Portrait Harriett Baldwin
- Hansard - - - Excerpts

I did not say that in updating the House there would necessarily be anything new, but I do want to reiterate the commitments that I have previously made.

The work will benefit suppliers across the country, injecting an estimated £200 million into the UK supply chain and sustaining 1,600 high-quality jobs, an estimated 600 of which—more than a third—are in Scotland. From Loanhead in Midlothian, where the helicopter handling equipment will be built, to Fleet in Hampshire, where communications equipment will be developed; from Dunfermline in Fife, where the steering gear will be built, to Huddersfield in West Yorkshire, as mentioned by my hon. Friend the Member for Colne Valley (Jason McCartney), where the gearboxes will be constructed—this investment is good news for UK industry. Furthermore, we announced in July the latest commitment of £183 million to buy the maritime indirect fires system—the five-inch gun—for the first three ships. That takes our total investment in the Type 26 programme so far to £1.8 billion, which is hard evidence not only of our commitment to the programme but of real progress in delivery.