Maritime Patrol Aircraft: Procurement

(asked on 10th January 2022) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what CDEL costs have been budgeted; what RDEL costs have been budgeted for the P-8A ; and when he projects FOC will be achieved for the UK's P-8A aircraft.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 17th January 2022

Full Operating Capability is scheduled for April 2024. The following CDEL and RDEL figures are budgeted:

CDEL £1.625 billion

RDEL £0.240 billion