Roads: Ely

(asked on 17th January 2024) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what estimate he has made of the (a) cost and (b) completion date of the proposed A10 Ely-Cambridge road project.


Answered by
Guy Opperman Portrait
Guy Opperman
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 25th January 2024

The A10 Ely to Cambridge improvement scheme is being promoted by Cambridgeshire County Council and Cambridgeshire and Peterborough Combined Authority for consideration for potential funding as part of the Department’s Major Road Network / Large Local Majors (MRN / LLM) programme. It would not form part of the Government's Road Investment Strategy.

The promoters are currently developing an Outline Business Case (OBC) for the scheme which they expect to submit to the Department in August for a decision on whether to approve it and provide conditional support for the scheme as part of the MRN/ LLM programme.

The latest scheme cost estimate and completion date provided to the Department are £234 million and September 2030 respectively. Naturally, this cost estimate and completion date may be subject to change.