AWACS

(asked on 7th December 2022) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, for what reason there is a delay in the E-7 Wedgetail aircraft fleet reaching full operational capability.


Answered by
Alex Chalk Portrait
Alex Chalk
Lord Chancellor and Secretary of State for Justice
This question was answered on 12th December 2022

There have been several reasons behind delays to the E-7 Wedgetail schedule including the Covid-19 pandemic, and global supply chain and resourcing challenges affecting the aerospace and defence industries, exacerbated by the war in Ukraine and a hurricane impacting the radar production facility.

The Ministry of Defence and Boeing are working closely to identify opportunities to minimise the delays, and the detailed schedule, including the Full Operating Capability, will be confirmed when the Full Business Case is finalised in mid-2023.