To ask the Secretary of State for Transport, whether she plans to extend land powers for the HS2 route between Birmingham and Crewe beyond 10 February 2025; and what assessment she has made of the potential impact of those powers lapsing on future northern rail connectivity.


Answered by
Keir Mather Portrait
Keir Mather
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 4th February 2026

The Northern Growth Strategy set out the Government’s intention to ultimately deliver a full North-South new line between Birmingham and Manchester. As part of this announcement, the Government confirmed that its existing land holdings between the West Midlands and Crewe will be retained.

We are aware that the existing land acquisition powers for the HS2 Phase 2a route expire in February 2026. We will set out our future intentions shortly.