Lower Thames Crossing: Excavation

(asked on 3rd February 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what proportion of soil excavated as part of the Lower Thames Crossing construction will be a) re-used on site, b) recycled or c) disposed of off-site.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 11th February 2026

The Lower Thames Crossing project aims to reuse between 90% and 95% of the soil it excavates on site. This material will be used to create new public parks, embankments and earth bunds, helping to screen the route from the local community. The remaining material will be disposed of off-site. Details of how this material will be treated have not yet been determined; however, this information will be set out in the project’s Delivery Partners’ Site Waste and Materials Handling Plans, which, once completed and approved by the Secretary of State, will be published on the Lower Thames Crossing website.

Reticulating Splines