LE TacCIS Programme

(asked on 23rd February 2022) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, for what reason the costs of the Morpheus programme were excluded from the Equipment Plan.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 3rd March 2022

The costs of Morpheus programme are included in the equipment plan. The NAO's recent equipment plan reporthighlights that the funding included in the 2021 equipment plan is less than cost modelling produced by the delivery agent based on earlier assumptions about the programme.