HMS Prince of Wales: Repairs and Maintenance

(asked on 14th December 2020) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, pursuant to the Answer of 14 December 2020 to Question 126964 on HMS Prince of Wales: Repairs and Maintenance, what estimate he has made of the cost of the repairs.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 17th December 2020

The estimated incremental cost of the repair work is £3.3 million.

Remedial work being conducted on both Queen Elizabeth Class Carriers to help prevent a repetition of this event is expected to cost £2.2 million.