To ask the Secretary of State for Defence, with reference to the oral evidence given by Ms Cat Little to the Public Accounts Committee on 14 March 2018, HC 880, whether his Department expects the projected costs of the Dreadnought programme to increase.


Answered by
Guto Bebb Portrait
Guto Bebb
This question was answered on 30th April 2018

As the Prime Minister announced in Parliament on 28 March (Official Report, column 756), the Ministry of Defence has been given access to £600 million in 2018-19 from the £10 billion contingency for the Dreadnought programme announced in the 2015 Strategic Defence and Security Review. This will allow us to drive out cost and risk later in the programme and ensures best value for the taxpayer. This will ensure the Dreadnought programme remains on track to be delivered on time and within its overall £31 billion forecast.