Railways: Midlands

(asked on 18th July 2023) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the (a) projected end date is, (b) forecast spend in the financial year 2023-24 is, (c) initial planned whole life costs were and (d) delivery confidence assessment is of the Midlands Rail Hub programme; and when each of those figures were last reviewed.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 24th July 2023

The Midlands Rail Hub is projected to enter service in the early 2030s, and the forecast spend in 2023/24 is £7.98m. Initial planned whole life costs (at the time of the 2019 Strategic Outline Business Case) were £1,544m. The Delivery Confidence Assessment remains Amber, as set out in the Infrastructure and Projects Authority Annual Report. This detail is reviewed quarterly in line with the requirements of the Government’s Major Projects Portfolio.