Wind Power

(asked on 2nd July 2014) - View Source

Question

To ask the Secretary of State for Energy and Climate Change, what the capacity is of onshore wind that started generation in (a) May to December 2010, (b) 2011, (c) 2012, (d) 2013 and (e) January to June 2014 and began construction (i) before May 2010 or (ii) after May 2010.


Answered by
 Portrait
Lord Barker of Battle
This question was answered on 14th July 2014

The Department does not collect data on when renewable project commences generation or when they start construction.

It does however collect data, through the Renewable Energy Planning Database (https://restats.decc.gov.uk/app/reporting/decc/monthlyextract), on when renewable projects become fully operational. In terms of installed capacity, the figures for renewable energy projects that became fully operational are:

Total

Hydro

Onshore wind

Offshore wind

Solar > 5MW

All renewables

Capacity (MW)

Capacity (MW)

Capacity (MW)

Capacity (MW)

Capacity (MW)

May to Dec 2010

3.45

475.493

300

0

833.5792

2011

5.138

463.207

183.6

0

933.8319

2012

11.3379

1317.841

1154.6

11.5

2718.4186

2013

3.6391

1432.7145

974.1

346.525

4016.7711

Jan to May 014

6.52

78.545

0

577.99

848.949

Total

30.085

3767.8005

2612.3

936.015

9351.5498

Reticulating Splines