Trident Submarines

(asked on 24th November 2014) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, how much his Department has spent on each long lead item for the Successor submarine; and how much his Department has spent on the Successor submarine programme to date.


Answered by
Philip Dunne Portrait
Philip Dunne
This question was answered on 1st December 2014

As of 31 March 2014, the Ministry of Defence had committed £230 million for long lead items. From within this, the following individual items have been ordered:

Weapon Handling and Launch System, at a cost of £11.8 million;

Gearbox and associated equipment, at a cost of £6.6 million;

Pressurised Water Reactor 3 reactor plant and associated main propulsion systems, at a cost of £58.8 million;

Since 31 March 2014, additional orders have been placed with the US Department of Defense as follows:

Material to support the manufacture of missile tube components, at a cost of $27.4 million;

Missile Tube Long Lead Materials, at a cost of $52.8 million; and

Material to support the manufacture of integrated tube and hull fixtures, at a cost of $7.6 million.

This level of commitment is in line with the Initial Gate approval.

The total programme spend at the end of financial year 2013-14 was £2,068 million.

Reticulating Splines