Nuclear Power Stations

(asked on 15th January 2015) - View Source

Question

To ask the Secretary of State for Energy and Climate Change, what proportion of the Nuclear Decommissioning Authority's budget he expects to be spent on decommissioning and cleaning up nuclear plants in (a) 2014-15 and (b) 2015-16.


Answered by
Matt Hancock Portrait
Matt Hancock
This question was answered on 21st January 2015

The Nuclear Decommissioning Authority expects the proportion of its expenditure through its Site Licence Companies that is used for decommissioning, as defined for the purposes of the Department of Energy and Climate Change’s Annual Report and Accounts, to be 37% in 2014-15 and 41% in 2015-16. The remainder of this budget will be spent on waste and nuclear materials management, commercial operations and support costs.