Question to the Ministry of Justice:
To ask the Secretary of State for Justice, with reference to page 11 of the House Commons Library Deposited Paper, DEP2019-0490, Prison Operator Competition Contract Summary, when the decision to appoint Kier as construction partner for HMP Wellingborough was made.
Kier were engaged by the Ministry of Justice using a two-stage contract. The first stage, which is primarily for the design of the prison, was executed on 14 February 2018. The second stage, which is primarily for the construction of the prison was executed on 15th April 2019