Buildings: Insulation

(asked on 27th June 2019) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Housing, Communities and Local Government, how many (a) private and (b) social sector buildings have not started work on removing and replacing ACM cladding.


Answered by
Kit Malthouse Portrait
Kit Malthouse
This question was answered on 3rd July 2019

As of 31 May 2019, a total of 146 private sector residential buildings, and 21 social sector residential buildings with Aluminium Composite Material cladding are yet to begin remediation. This information can be found as part of the latest Building Safety Programme Monthly Data Release at: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/807417/Building_Safety_Data_Release_-_May_2019.pdf