Question to the Ministry of Defence:

To ask the Secretary of State for Defence, on what date a MR44 aircraft was delivered to and accepted by the RAF; and if he will make a statement.


Answered by
Philip Dunne Portrait
Philip Dunne
This question was answered on 18th April 2016

None of the Nimrod MRA4 aircraft were delivered and accepted by the RAF. At the time the programme was cancelled it was 114 months late and nearly £800 million over budget.