To ask the Secretary of State for Defence, whether his Department has updated estimates of the cost of the Successor submarine programme since the publication of the Strategic Defence and Security Review 2015.


Answered by
Philip Dunne Portrait
Philip Dunne
This question was answered on 18th April 2016

No. As stated in the Strategic Defence and Security Review 2015, our latest estimate is that manufacturing the four Successor submarines is likely to cost a total of £31 billion, including inflation over the lifetime of the programme. We will also set a contingency of £10 billion.