AWACS: Procurement

(asked on 1st May 2020) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, with reference to the Defence and Equipment Plan 2019-2029, published on 27 February 2020, for what reasons the cost of the UK's 5 E-7 Wedgetail AWACS has increased by from £1.51 billion to £2.16 billiionn since the announcement of the purchase of that aircraft in March 2019.


Answered by
Jeremy Quin Portrait
Jeremy Quin
This question was answered on 6th May 2020

The cost of the acquisition of the E-7 Wedgetail aircraft has not increased. The figure of £1.51 billion relates to the value of the aircraft procurement contract, whereas the figure of £2.16 billion refers to the approved project costs, the scope of which covers more than just the acquisition of the aircraft including work on infrastructure and training and on future support/sustainment, hence the larger amount.