Question to the Ministry of Justice:
To ask the Secretary of State for Justice, what maintenance work is required at HMP Wandsworth as of 14 December 2023.
A project to replace CCTV across the whole prison is due to complete in April 2025. A site-wide programme of fire safety improvements and refurbishment of showers is due to commence in January 2024. A further programme of window replacements is planned to commence in April 2024. Two further projects are currently in development in HMP Wandsworth: one to replace the chapel roof and another to refurbish or replace the recycling centre. Those will be considered for funding in future financial years.