National Grid: Scotland

(asked on 27th October 2022) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, pursuant to the Answer of 6 September 2022 to Question 40864 on National Grid: Scotland, if he will make an estimate of the cost of delivering the Eastern High Voltage Direct Current Link scheme via overland pylons.


Answered by
Graham Stuart Portrait
Graham Stuart
This question was answered on 2nd November 2022

The Eastern High Voltage Direct Current Link scheme is a joint project between the three private electricity transmission network companies in Great Britain. Eastern Links 1 and 2 have received Final Needs Case approvals from Ofgem based on estimated combined capital costs (not lifetime costs) of £3.4bn.

The Electricity System Operator’s Holistic Network Design, a blueprint for offshore and onshore transmission projects required to support Government’s ambition for 50GW of offshore wind capacity by 2030, confirmed the need for the Eastern Links 1 and 2. The Holistic Network Design is estimated to save consumers £5.5bn over the network asset lifetime.

Reticulating Splines